PAID Bond Financing Program
 

Process and Timing

Application Schedule

(Process takes approximately 8-10 weeks, 12-14 for manufacturing projects)
Week #1 Tax Clearance Form due to PAID
(After completing, please fax/mail completed form with authorized signature to PAID)
Week #2 TEFRA Notice due to PAID
Week #3 TEFRA Notice to appear in local newspaper
Week #4 Bond Financing Application (BFA) and $2,000 Application Fee due to PAID
(Please fax/mail page 6 with authorized signature to PAID)
Week #5 TEFRA Hearing and PAID Board Meeting
Week #6 BFA sent to Department of Community and Economic Development (DCED) for approval
Week #7 DCED reviews BFA for approval
Week #8 DCED reviews BFA for approval
Week #9 Expect Notice of DCED approval
Week #10 Expect Notice of DCED approval
Prepare for Closing/Form 8038
  (Process continues for manufacturing projects only)
Week #11 Preliminary Allocation Request (PAR) form sent to DCED
Week #12 DCED reviews PAR for approval
Week #13 DCED reviews PAR for approval
Week #14 Expect Notice of DCED PAR approval
  Prepare for Closing
Final Allocation Request (FAR) form and IRS form 8038 to DCED 15 days after closing.
 